What Is External Plastering?
External plastering (rendering) is the multi-layer build-up applied to exterior blockwork or concrete to provide weather protection and a consistent finish ready for paint or a pressed/tyrolean texture. On mixed substrates (block to columns/beams/slabs), we reinforce junctions to avoid cracking and ensure a uniform, durable façade.
Our Site Sequence (AmtaarGC)
- Access & Safety
- Erect and tie scaffolding with handrails and safe access; audit before works begin.
- Substrate Prep
- Clean surfaces; hack off fins; remove oils/grease/dust by scrubbing.
- Fill chases/holes around M&E; fix services before plastering.
- Reinforce all block-to-concrete junctions with approved lathing/mesh using slurry.
- Key Coats & Base Render
- Pre-wet surfaces.
- Apply 3–5 mm 1:3 cement:sand coat including waterproofing additive per data sheet.
- Same day, dash a slurry key (≈400 kg cement to 1.0 m³ clean sand) pneumatically or manually.
- Cure with water for ≥24 hrs.
- Apply main plaster/render 10–20 mm (min 10 mm) at 1:4 cement:sand; cure ≥48 hrs.
- Finish Options (Tyrolean/Pressed)
- First tyrolean: 1 part white Portland cement : 2 parts fine aggregate, applied uniformly.
- Second/final tyrolean: also 1:2 (white cement:fine aggregate), with colour additives to approved sample, then mechanically flattened to a pressed finish if specified. Cure ≥48 hrs.
- Form sloped horizontal joints where plaster meets stonework; waterproof those junctions.
- Details, Protection & QA
- Install marble/stone cills after plasterwork; make good as needed.
- Keep sites clean; do not re-temper set mixes.
- QC with straight edges, plumb lines and checks for verticality/horizontal control using screeds/spacers.
- Skilled trades throughout; protect adjacent works.
Typical Build-Ups We Deliver
- Traditional cement:sand render with waterproofing additives and tyrolean/pressed finish.
- Reinforced junctions at block/RC interfaces to control cracking.
- Weather-managed curing and staged program to suit London conditions.
What Drives Cost?
- Access (full-height scaffold vs towers), substrate condition, junction reinforcement, finish complexity (e.g., two-stage tyrolean with colour), and QA/defect prevention (cure times, weather protection). We scope these items upfront so there are no surprises.
Common Failure Points We Avoid
- Skipping the slurry key or curing windows → poor adhesion and hairline cracking.
- Not reinforcing junctions → reflective cracks at columns/beams/slabs.
- Re-tempering partially set mixes → weak, patchy render.

