šŸ—ļø The Complete Guide to Building Control–Approved Foundations Under Ā£15,000 (Using One-Day Milestone Management)

Most homeowners believe foundations for a rear extension, side extension, or 40 sqm permitted development build must cost Ā£20,000–£35,000. This is the biggest myth in domestic construction. The truth is simple: A foundation is a one-day operation when managed correctly. By using a task/milestone workflow, prefabricated components, and the correct Building Control sequence, a full foundation system — including strip footings, reinforcement, manhole installation, hardcore, DPM, insulation, and a ground-bearing slab — can be delivered for Ā£10,150–£14,500, fully compliant with UK Building Regulations. This blog shows the exact steps, the correct Building Control inspections, and the project management method that makes this possible.

1. Site Clearance & Preparation

Keywords: site clearance London, groundworks for extensions, mini digger hire**

The first step is a clean working zone:

  • Remove slabs, concrete pads, vegetation
  • Create a flat access route for equipment
  • Prepare for excavation

Building Control Requirement:
A clean, uncontaminated surface that exposes natural ground.

Why it saves money:
Clear everything before the digger arrives = only one digger shift is needed.


2. Excavation of Strip Foundations

Keywords: strip foundation excavation, 600mm wide trenches, 1m deep foundations**

A typical 40 sqm extension requires:

  • 600mm wideĀ trench
  • 1m deepĀ (depending on trees/soil)
  • 18–20 linear metresĀ of excavation

This is normally completed in 2–3 hours with a mini digger and operator.


3. Building Control Inspection #1 — Foundation Excavation

Building Control checks:

  • Soil bearing quality
  • Depth of excavation
  • Width and shape of trench
  • No loose fill or soft spots
  • Drain and tree influence

Only after approval should reinforcement or concrete be placed.

Project Management Rule:
Never call Building Control early. Only call when 100% of the trench is ready.
This eliminates repeat visits and avoids failed inspections.


4. Reinforcement Installation (Prefabricated Cages)

Keywords: rebar foundation cage, T12/T16 reinforcement, structural engineer design**

Because reinforcement is prefabricated off-site, installation is fast:

  • Lift into trench
  • Set on spacers for correct cover
  • Tie laps and corners

This replaces what used to take a full day of steel fixing with a 2-hour task.

Why it saves money:
You eliminate manual bending, cutting, tying on site — the biggest hidden labour cost.


5. Prefabricated Manhole Installation

Keywords: foul drainage connection, prefabricated manhole, extension drainage UK**

Traditional brick-built manholes take 1–2 full days.

Your system uses prefabricated manhole chambers, installed in under 2 hours, correctly aligned with the new extension drainage.

Why it saves money:
One manhole installation = 2 hours, not two days.


6. Ready for Concrete — And This Is Where Project Management Matters

Most builders pour concrete badly because they spread the work across 2–3 days.

Your method is different.

You book labour for a milestone, not a day.

The concrete milestone includes:

  • 2 hrsĀ pumping and placing concrete
  • 2 hrsĀ clearing and grading
  • 2 hrsĀ installing prefabricated manhole
  • 2 hrsĀ installing prefabricated rebar + membrane

This creates an organised, predictable 8-hour workflow.


7. Concrete Pour (The 2-Hour Rule)

Keywords: C30 concrete, foundation concrete cost UK, pump pour extension**

Concrete has a 2-hour usable life.
Once the wagon arrives, the clock begins.

During this window:

  • Pump concrete into trench
  • Level & compact
  • Ensure correct height
  • Finish surface cleanly

Because you install reinforcement and manholes before the pour, the entire operation flows perfectly.

Concrete Cost Calculation

Concrete required: 7 m³
Rate: Ā£170/m³

Total = Ā£170 Ɨ 7 = Ā£1,190 (approx.)

This is why foundations are affordable when managed properly.


8. Backfill, Hardcore & Compaction

After the foundation sets:

  • Backfill the sides
  • Install Type 1 hardcore
  • Compact in layers

Building Control Requirement:
No soft spots, light compaction test, proper levels.


9. DPM, Insulation & Mesh for Ground Slab

Keywords: DPM, insulation, A142 mesh, ground slab extension**

This includes:

  • 1200 gauge DPM
  • Rigid insulation to meet U-values
  • A142 mesh reinforcement
  • Edge insulation upstands
  • Service penetrations & ducts

10. Building Control Inspection #2 — Slab Preparation

BC checks:

āœ” Hardcore compaction
āœ” DPM and moisture protection
āœ” Insulation thickness
āœ” Mesh lap and position
āœ” Drainage layout

Approval granted → ready for concrete.


11. Ground Slab Pour (Final Concrete Stage)

The slab is cast at:

  • 150mm thick
  • C25/C30 grade
  • Laser-levelled finish

This completes every structural element below the wall level.


šŸ’· Updated & Accurate Cost Breakdown (Final Numbers)

ItemCost Range
Excavation & digger hireĀ£300–£400
3-man ground team (2 days)Ā£1,700–£2,300
Concrete for strip foundationsĀ£1,200–£1,500
Concrete for slabĀ£900–£1,400
Steel rebar & reinforcement mesh£2,000
Hardcore, DPM, insulationĀ£600–£1,500
Skip / waste removalĀ£1,750–£2,800
Misc materials & ductsĀ£1,200–£1,600
ContingencyĀ£500–£1,000

šŸ”¢ Final Total Calculation

Minimum Total:

£300 + £1,700 + £1,200 + £900 + £2,000 + £600 + £1,750 + £1,200 + £500
Ā£10,150

Maximum Total:

£400 + £2,300 + £1,500 + £1,400 + £2,000 + £1,500 + £2,800 + £1,600 + £1,000
Ā£14,500


šŸŽÆ FINAL TOTAL RANGE: Ā£10,150 – Ā£14,500

Building Control approved. Fully compliant. Delivered efficiently. Zero waste.

This is why foundations do NOT cost Ā£25,000–£35,000.
They only cost that when the builder does not manage the day correctly.


šŸš€ Why This Method Works Every Time

Because the system is built around:

1. Milestones, not day rates

2. Prefabricated components

3. Concrete’s 2-hour life cycle

4. Zero downtime

5. Correct Building Control timing

6. One continuous workflow

This is engineering.
This is planning.
This is why your system beats traditional residential construction.

Leave a Reply

Your email address will not be published. Required fields are marked *

Speak to Our Lead Engineer Now