1. Site Clearance & Preparation
Keywords: site clearance London, groundworks for extensions, mini digger hire**
The first step is a clean working zone:
- Remove slabs, concrete pads, vegetation
- Create a flat access route for equipment
- Prepare for excavation
Building Control Requirement:
A clean, uncontaminated surface that exposes natural ground.
Why it saves money:
Clear everything before the digger arrives = only one digger shift is needed.
2. Excavation of Strip Foundations
Keywords: strip foundation excavation, 600mm wide trenches, 1m deep foundations**
A typical 40 sqm extension requires:
- 600mm wideĀ trench
- 1m deepĀ (depending on trees/soil)
- 18ā20 linear metresĀ of excavation
This is normally completed in 2ā3 hours with a mini digger and operator.
3. Building Control Inspection #1 ā Foundation Excavation
Building Control checks:
- Soil bearing quality
- Depth of excavation
- Width and shape of trench
- No loose fill or soft spots
- Drain and tree influence
Only after approval should reinforcement or concrete be placed.
Project Management Rule:
Never call Building Control early. Only call when 100% of the trench is ready.
This eliminates repeat visits and avoids failed inspections.
4. Reinforcement Installation (Prefabricated Cages)
Keywords: rebar foundation cage, T12/T16 reinforcement, structural engineer design**
Because reinforcement is prefabricated off-site, installation is fast:
- Lift into trench
- Set on spacers for correct cover
- Tie laps and corners
This replaces what used to take a full day of steel fixing with a 2-hour task.
Why it saves money:
You eliminate manual bending, cutting, tying on site ā the biggest hidden labour cost.
5. Prefabricated Manhole Installation
Keywords: foul drainage connection, prefabricated manhole, extension drainage UK**
Traditional brick-built manholes take 1ā2 full days.
Your system uses prefabricated manhole chambers, installed in under 2 hours, correctly aligned with the new extension drainage.
Why it saves money:
One manhole installation = 2 hours, not two days.
6. Ready for Concrete ā And This Is Where Project Management Matters
Most builders pour concrete badly because they spread the work across 2ā3 days.
Your method is different.
You book labour for a milestone, not a day.
The concrete milestone includes:
- 2 hrsĀ pumping and placing concrete
- 2 hrsĀ clearing and grading
- 2 hrsĀ installing prefabricated manhole
- 2 hrsĀ installing prefabricated rebar + membrane
This creates an organised, predictable 8-hour workflow.
7. Concrete Pour (The 2-Hour Rule)
Keywords: C30 concrete, foundation concrete cost UK, pump pour extension**
Concrete has a 2-hour usable life.
Once the wagon arrives, the clock begins.
During this window:
- Pump concrete into trench
- Level & compact
- Ensure correct height
- Finish surface cleanly
Because you install reinforcement and manholes before the pour, the entire operation flows perfectly.
Concrete Cost Calculation
Concrete required: 7 m³
Rate: £170/m³
Total = £170 à 7 = £1,190 (approx.)
This is why foundations are affordable when managed properly.
8. Backfill, Hardcore & Compaction
After the foundation sets:
- Backfill the sides
- Install Type 1 hardcore
- Compact in layers
Building Control Requirement:
No soft spots, light compaction test, proper levels.
9. DPM, Insulation & Mesh for Ground Slab
Keywords: DPM, insulation, A142 mesh, ground slab extension**
This includes:
- 1200 gauge DPM
- Rigid insulation to meet U-values
- A142 mesh reinforcement
- Edge insulation upstands
- Service penetrations & ducts
10. Building Control Inspection #2 ā Slab Preparation
BC checks:
ā Hardcore compaction
ā DPM and moisture protection
ā Insulation thickness
ā Mesh lap and position
ā Drainage layout
Approval granted ā ready for concrete.
11. Ground Slab Pour (Final Concrete Stage)
The slab is cast at:
- 150mm thick
- C25/C30 grade
- Laser-levelled finish
This completes every structural element below the wall level.
š· Updated & Accurate Cost Breakdown (Final Numbers)
| Item | Cost Range |
|---|---|
| Excavation & digger hire | Ā£300āĀ£400 |
| 3-man ground team (2 days) | Ā£1,700āĀ£2,300 |
| Concrete for strip foundations | Ā£1,200āĀ£1,500 |
| Concrete for slab | Ā£900āĀ£1,400 |
| Steel rebar & reinforcement mesh | £2,000 |
| Hardcore, DPM, insulation | Ā£600āĀ£1,500 |
| Skip / waste removal | Ā£1,750āĀ£2,800 |
| Misc materials & ducts | Ā£1,200āĀ£1,600 |
| Contingency | Ā£500āĀ£1,000 |
š¢ Final Total Calculation
Minimum Total:
£300 + £1,700 + £1,200 + £900 + £2,000 + £600 + £1,750 + £1,200 + £500
= £10,150
Maximum Total:
£400 + £2,300 + £1,500 + £1,400 + £2,000 + £1,500 + £2,800 + £1,600 + £1,000
= £14,500
šÆ FINAL TOTAL RANGE: Ā£10,150 ā Ā£14,500
Building Control approved. Fully compliant. Delivered efficiently. Zero waste.
This is why foundations do NOT cost Ā£25,000āĀ£35,000.
They only cost that when the builder does not manage the day correctly.
š Why This Method Works Every Time
Because the system is built around:
1. Milestones, not day rates
2. Prefabricated components
3. Concreteās 2-hour life cycle
4. Zero downtime
5. Correct Building Control timing
6. One continuous workflow
This is engineering.
This is planning.
This is why your system beats traditional residential construction.

