1. Scope
Provide materials, labour, plant, supervision, inspections, and tests to cast RC tank walls to the required dimensions, finish, and watertight performance. Includes setting-out, reinforcement, embedded items/sleeves, formwork, concrete supply/placement/compaction, curing, formwork striking, defect repair, and records.
2. References (project-specific to be inserted)
- Approved construction drawings & bar bending schedules
- Project specs for structural concrete & water-retaining structures
- Relevant standards (e.g., BS EN 1992, BS EN 13670, BS EN 12350/12390)
- Project ITP, QCP, and HSE plan
3. Responsibilities
- Project/Site Engineer: setting-out, coordination, inspections, records.
- QC Engineer: ITP compliance, material approvals, cube tests, NCR control.
- HSE Officer: risk assessments, briefings, permits, housekeeping.
- General Foreman: resources, sequencing, workmanship.
- MEP Coordinator: sleeves/openings verified before pour.
4. Resources
- Materials: approved reinforcement & spacers, formwork materials, shutter release, concrete to specified grade/exposure, waterstops where required.
- Plant/Equipment: concrete pump, vibrators (primary + standby), total station/levels, lifting gear, curing equipment.
- PPE & HSE: as per task risk assessment and method statements.
5. HSE & Site Controls
- Toolbox talk and permit-to-pour prior to each casting operation.
- Edge protection, working platforms, and safe access/lighting.
- Only competent operators on pumps, vibrators, lifting gear.
- Housekeeping to keep pour routes clear; emergency spill kit ready.
6. Procedure
6.1 Setting-Out
- Confirm wall alignment, thickness, and levels from benchmarks.
- Verify kicker/keys and construction joints as detailed.
6.2 Reinforcement Fixing
- Install rebar per approved schedules; maintain cover using approved spacers.
- Clean substrate and reinforcement; remove laitance/debris from kicker.
- Provide waterstops at construction joints where specified.
- Raise Inspection Request (IR) minimum 24 hours before pour for rebar & formwork pre-close checks.
6.3 MEP/Openings
- Fix sleeves/box-outs/inserts exactly to coordinated MEP/shop drawings.
- Raise separate IR for MEP penetrations and obtain clearance prior to shutter close.
6.4 Formwork Erection
- Use modular/formwork system suitable for hydrostatic pressure of wall pour.
- Treat contact faces with approved release agent; ensure tight joints.
- Provide braces/ties as per system design; check plumb/line and stability.
- Close form with water-tight tie systems and seals; clean and blow out.
6.5 Pre-Pour (Hold Point)
- Conduct pre-pour IR: dimensions, alignments, cleanliness, embedments, access, lighting, pump reach, vibrator availability, cube/testing plan, curing materials ready.
- Confirm concrete class, slump, max aggregate, and admixtures approved.
6.6 Concrete Delivery, Placement & Compaction
- On arrival: verify temperature & slump; reject non-conforming loads.
- Place in layers ~300 mm; limit free drop to ≤1.5 m; avoid segregation.
- Poker vibrate each layer thoroughly; do not vibrate rebar directly; overlap zones to eliminate voids/honeycombs; avoid over-vibration.
- Maintain continuous pour to prevent cold joints; if unavoidable, form as detailed with waterstops/surface preparation.
6.7 Finishing & Curing
- Close to finished level; seal around protrusions/sleeves as required.
- Begin curing immediately (membrane, wet hessian, or forms retained) to specified duration; protect from shock, vibration, and thermal extremes.
6.8 Striking (De-shuttering)
- Observe minimum striking times and confirm sufficient in-situ strength.
- Never use crane to “break” cohesion—use proper wedges/pry bars; remove ties in sequence while maintaining stability; protect arrises.
6.9 Defects & Repairs
- Inspect for honeycombs, fins, blowholes; repair with approved method/material after Consultant/QC agreement. Continue curing after repair.
7. Quality Control & Tolerances
- Dimensional: section ±5 mm (≤400 mm thickness), verticality 1/500, position and level per project tolerances.
- Surface: free from voids, tie-hole treatment as specified.
- Testing: cubes/cores as per ITP (typ. one set per agreed volume or pour), plus slump/temperature records; water-tightness/hydrotest per spec.
8. Inspection & Testing Plan (ITP) – Typical Hold/Witness Points
- Rebar & Waterstop Inspection (HOLD) – cleanliness, cover, laps, anchors.
- Formwork Pre-Close (HOLD) – alignment, pressure bracing, seals.
- MEP Penetrations (WITNESS/HOLD) – locations, sizes, sleeves.
- Pre-Pour (HOLD) – materials approvals, test plan, access & safety.
- Concrete Tests (WITNESS) – slump/temperature/cubes per load/shift.
- Post-Pour (WITNESS) – finish, curing, records.
- Striking (WITNESS) – timing, stability, surface checks.
- Defect Repair (WITNESS) – method & acceptance.
9. Records & Documentation
- IRs, cube results, delivery tickets, calibration certificates (pump/vibrators), manpower/plant logs, as-built surveys, NCRs/CARs (if any), strike records, and curing log.
10. Acceptance Criteria
- Dimensions and verticality within tolerance; surface sound and repaired areas accepted; test results meeting specified strength; watertightness confirmed by specified hold test (e.g., 24–72 h hydrotest or equivalent).

